IIT Roorkee (GNEC), Greater Noida
Envirowaste2wealth Pvt. Ltd. successfully designed and developed a comprehensive sewerage network system for the IIT Roorkee Greater Noida Centre (GNEC)
campus. The project was planned to manage wastewater generated from a design population of 200 persons, following CPHEEO Manual (2013) guidelines.
The scope included assessment of site conditions, estimation of wastewater flows, consideration of groundwater infiltration, and application of appropriate
peak factors for system sizing. The sewerage system was designed with a water demand of 135 LPD, sewage generation of 108 LPD (0.8 interception factor),
and peak factor of 3, ensuring reliable and efficient wastewater management for the campus.